Issue Management Methodology for Tracking Project IssuesProject Planning Kit - Templates for Project Managers including plans, processes, forms and free tools.

An issue is an incident, circumstance, problem or inquiry that affects or potentially affects the timely delivery of the project, product or service, it may also impact the quality of deliverables and the cost of production.

Some projects are ongoing and the definition of an issue is a little different.

A help desk defines an issue as a request for help that requires a response. A service department keeps track of service requests as issues. A software maintenance group tracks reports of software bugs and enhancement requests as issues.

Issue Management

Because of the impact issues have on a project, product development or ongoing service, issue management is an important aspect in any management methodology. This issue management methodology promises to make the handling of issues a seamless part of your larger scoped methodologies rather than a process separate from them.

It is usually not hard for team members to identify issues, but it is still worth having a working definition of an issue. Remember that the more ambitious your project the more issues will arise.

Action item: The project team must be made aware of what issues are, provide some examples, and ask other team members to provide some examples.

2. Requirements

A central repository of issue information easily accessible to all team members, because it is good for team morale and productivity to know that their issues are being addressed.

Action item: Choose a central repository for your issues.

An issue manager is the person chosen to oversee all issues. It can be the project manager, team leader or another person in a responsible leadership position. The issue manager is responsible for making sure that there is consistent, disciplined and continuous progress made on all issues. The issue manager is accountable to upper management for the progress made on all issues. The issue manager communicates issue progress to the team, upper management and all stakeholders.

Action item: Appoint an Issue Manager and notify the issue manager of their role and responsibilities.

This issue management methodology represents best practice for managing issues. However, the goal is to have a successful project, product development or service, the goal is not to follow a methodology fanatically.

Action item: Adapt the methodology so your project's success is maximized.

3. Steps

3.1 Discovery

Issues can arise at any time. When an issue is discovered it is recorded in the central repository.

It is important to allow issues to be recorded by a broad group of people including team members, upper management, users, customers, stakeholders, vendors and contractors. It is important because if there are barriers to reporting an issue then there is an increased chance that the issue will go unrecorded. You cannot address issues that you do not know about. It is not necessary that everyone has access to central repository, but the more you can allow the better.

Action item: Set up access to the central repository for those people that need it.

3.2 Recording

Training people to identify issues is often unnecessary, however getting people to record the issue in the central repository will take some training and encouragement. For example, a team member may mention an unrecorded issue to the project manager during a coffee break or other informal occasion, this team member needs some encouragement to record such issues in the central repository.

For all kinds of issues, prevention is better than correction. Also, issues tend to be less severe if they are addressed earlier rather than later. This means that every effort should be made to report issues as soon as they are discovered, instead of waiting for the issue to become "serious enough" before recording it. Do not be afraid of duplicating an issue or overlapping with existing issues, it is better than missing an issue.

A complete description of the cause of the issue should be recorded in the central repository. Resist the temptation to describe the issue in terms of a solution. Any implication of the issue should be recorded. Attach any supporting documentation, screenshots, report output, faxes, error messages and other media that describes the issue.

The person who is recording the issue can make a recommendation for a solution, if they have one. This person should also assign the issue if possible, even if it is only assigned to the issue manager for re-assignment.

When an issue is initially recorded it should be recorded in the central repository with a status code that reflects the fact that it is new issue and has not been reviewed. An attempt should also be made to categorize and rank the severity of the issue.

Many teams describe issues in terms of the desired solution, leaving others to deduce the actual issue. This is not best practice since it limits the scope of possible creative solutions. As an example a badly worded issue: "We need more people." There is no indication in this example of what the issue actually is, so finding alternative solutions is impossible. If the example issue had been worded as "The shipping department has swamped us with product, there is a possibility of spoilage if we cannot get the product delivered." With the issue worded this way perhaps the shipping department can become aware of how there actions are causing issues down the line and adapt their actions.

3.3 Initial Review

The initial review is a triage of new issues. It is usually performed by the issue manager or deputies who are familiar with the scope and priorities of the project. If the team is small the entire team can meet for the review. For each new issue the status, category and severity are reviewed and the issue assigned to someone for action and optionally an owner is identified as follows.

Sometimes the same person who records the issue may be doing the initial review, so these two steps can be fused into one in this situation.

3.3.1 Issue Status

A decision is made about the next state of the issue. (The previous state was "new".) The next status of the issue reflects the nature and timing of the action to address the issue. It is one of the following:

open: immediate action will be taken to address the issue

deferred: action will be deferred until some future time

referred: action will be taken by some other group, probably because the issue is beyond the current scope

cancelled: no action will be taken now or in the future

3.3.2 Categorize the issue

A first attempt at categorizing the issue was made when it was first recorded. But, now during the initial review the category can be refined.

The proper issue category is helpful when prioritizing the resources required to address issues. It is especially useful for reporting purposes.

Action item: Discuss with the team how best to categorize the issues you expect to get, and document the categories that will be used.

3.3.3 Rank the issue severity

The severity reflects the importance of getting the issue resolved. Obviously, you want to direct resources at the most important issues before the lesser ones.

Action item: Choose a small set of severity codes that have a clear ranking. For example: Trivial, Standard, Important, Critical. Some people prefer: Low, Medium, High, Very High.

3.3.4 Assignment

From the start, the next person to take action on the issue must be assigned to the issue and notified.

If the issue description is incomplete, the issue can be assigned to the appropriate party to gather the information necessary to make the issue description clear.

Assign a person and not a group. Experience has shown that assigning issues to individuals leads to greater accountability than assigning issues to groups. An individual can be confronted about lack of progress, it is much harder to confront a group of people. A group can be represented by a group leader, so you can assign an issue to the group leader who will take action to reassign the issue to correct group member who will actually address the issue.

3.3.5 Ownership

It should be possible to decide which stakeholder is the owner of the issue. Having an issue owner is a way of recording who is accountable for the issue's resolution.

Owners must review the issues they own for progress to resolution. If the progress is not sufficient the issue manager should be told so that the situation can be remedied.

3.4 Taking Action

The process to address an issue iterates over the following sub-steps until the issue is resolved.

The person assigned to the issue, takes action to address the issue.

The person assigned to the issue, documents the action taken as an issue event in the central repository. An issue event has the person's name, the date and a description of the action taken.

If there is documentation to support the action taken, like a cost-benefit analysis of a proposed system change, the supporting files are attached to the issue.

The process of finding a solution may help refine the issue description. This refinement should be reflected in updates to the issue description and title, as well as attaching further supporting files. It may also require that the issue be re-categorized.

If the next iteration is the responsibility of another person the issue is reassigned.

If the issue is resolved in this iteration, the status is updated to reflect the fact that the issue is inactive.

3.5 Ongoing Oversight

Consistent and continuous evaluation of issues by the issue manager and the team must take place to bring the issues to resolution. This can take place through a periodic review of all active issues in the central repository with the team and a separate review with the stakeholders.

Escalate issues as needed by re-assigning or by changing issue ownership.

Report and communicate progress on all issues to upper management and to the team, subscriptions can be used by upper management and the team to follow progress on individual issues. This reporting can be integrated into project status reporting.

Analyze issue progress and adapt actions. The central repository should be able to provide feedback on how efficiently the issues are proceeding from creation to resolution. If it is taking too long to resolve important issues, then the issue manager must find ways to improve the turn-around time.

4. Finally

The following are a few further action items

Action item: Distribute copies of this issue management methodology to team members and stakeholders so that everyone knows how and why issues are managed.

Action item: Adapt and scale this issue management methodology to suit you project's scale and quirks.

Action item: Create your central repository, and get started today.

This issue management methodology has evolved over many years. It evolved from experience on projects with budgets from $500,000 to $50,000,000 which had a total number of issues ranging from a few hundred issues to many thousands. In half the cases the project team was physically dispersed in several countries.

Project Management Tutorials

Project Management Templates

Here are some Project Management templates you can get on our partner's site.

Change Management Kit - Templates for Project Managers to help you Initiate, Plan, Execute and Close projects while managing staff, customers, suppliers, change, risk, issues and quality. The Change Management Kit provides the documentation required to control changes to the scope, deliverables and resources within the project. The Change Request template allows staff to raise a change request within the project. Buy Now! Download these templates
Project Planning Kit - Templates for Project Managers including plans, processes, forms and free tools. The Project Planning Kit provides you with all of the project management templates, documents and forms required to plan a project by helping you to schedule time, cost and resources. Buy Now! Download these templates
Quality Management Kit - The Quality Management Kit includes a suite of templates used to assure and control the quality of deliverables within a project. The quality process helps you to implement Quality Assurance and Quality Control measures and the Quality Review Form will enable you to review the overall progress of your project. By using the Deliverables Register, you will be able to monitor and control the current quality of your project deliverables, thereby ensuring that they meet the quality targets set out in the Quality Plan. The Quality Management Kit includes a suite of templates used to assure and control the quality of deliverables within a project. Buy Now! Download these templates
Project Initiation Kit Project Initiation Kit
Start a new project by documenting a business case, undertaking a feasibility study, defining the project scope, recruiting key staff and locating them within a project office.
Buy Now! Download these templates
Project Execution Kit Project Execution Kit
Manage time, cost, quality, change, risks and issues during the execution of your project, as well as supplier procurement and customer acceptance.
Buy Now! Download these templates
Project Closure Kit Project Closure Kit
Helps close your project by handing over deliverables and documentation to the customer, terminating supplier contracts and releasing resources back to the business.
Buy Now! Download these templates

 



software testing templates

standard operating procedure templates

white paper templates

T e m p l a t e   S h o p

Action Plan Template

Audience Analysis Template

Availability Plan Template

Bill of Materials Template

Business Case Template

Business Continuity Plan Template

Business Plan Template

Business Process Design Template

Business Requirements Specification Template

Business Rules Template

Business Writing Services

Capacity Plan Template

Case Study Templates

Change Management Plan Template

Communication Plan Template

Concept of Operations Template

Configuration Management Plan Template

Conversion Plan Template

Datasheet Template

Deployment Plan Template

Disaster Recovery Template

Disposition Plan Template

Documentation Plan Template

Employee Handbook Template

Expression of Interest Template

Free

Free eBooks

Grant Proposal Template

Implementation Plan Template

Invitation To Tender Template

Market Research Templates

Marketing Plan Template

Operations Guide Template

Policy Manual Template

Project Plan Template

Proposal Manager Templates

Proposal Template

Release Notes Template

Request For Proposal Template

Risk Management Plan Template

Scope of Work Template

Service Level Agreement (SLA) Template

Small Business Video

Social Media Policy Templates

Software Development Lifecycle Templates

Software Testing Templates

Standard Operating Procedures Template

Statement of Work Template

System Administration Guide Template

Technical Writing Templates

technical writing templates

Test Plan Template

Training Plan Templates

Training Plan Templates

Troubleshooting Guide Template

Use Case Template

User Guide Template

White Papers

Work Instruction Templates

How to Write

Action Plans

Business Case

Business Writing

Business Proposals

Case Studies

Process Design

Project Management

Standard Operating Procedures Course

White Papers

Write for the Web

Grant Writing

Software Development Templates

 



Email Me Here

Endorsements | About Us | Contact Us | Site Map | Privacy | License | T&Cs | FAQs